BMW Group Plant Munich gears up for fully-electric future

News

In preparation for production of the fully-electric BMW i4, BMW Group Plant Munich will pause vehicle production for six weeks this summer.

Info

No cars will be produced between the end of the late shift on 23 July and the start of the early shift on 7 September. Plant Munich will take advantage of this break in production to implement numerous structural and remodelling measures before the fully-electric BMW i4 goes into standard production next year.

“We are gearing up our Munich plant for the future. Once remodelling is finished, we will be able to produce vehicles with diesel, petrol and hybrid drive trains, as well as the fully-electric BMW i4, all on the same line. This will allow us to respond flexibly to customer demand,” said Plant Director Robert Engelhorn.

Integrating the BMW i4 into the existing production system will be a major challenge for Plant Munich. The high-voltage battery makes the BMW i4 body concept different to that of the vehicle models previously built at the plant. Nevertheless, about 90% of the existing production systems used in the body shop can be integrated and enabled for future BMW i4 production. Only 10% - specifically, equipment used in production of the rear end - cannot be integrated, because of the high-voltage battery, and require new systems to be set up.

The high-voltage battery in the BMW i4 is installed from below. A new and separate battery assembly will be set up for this within vehicle assembly. “Confined structures make any remodelling and installation measures at Plant Munich particularly challenging. Old systems have to be removed, and new ones installed and put into service, in very tight spaces within six weeks. This takes meticulous planning and a lot of creativity,” underlined Engelhorn.

As well as installing new systems, existing production equipment will also have to be converted so the BMW 3 Series Sedan and BMW 3 Series Touring - both with combustion engines and hybrid drive train, the new BMW M3 and the fully-electric BMW i4 can all be produced on the same line.

This production interruption has been planned and prepared for since early 2019. Virtual reality (VR) is also being used across the board in transmission and final assembly to optimise future processes. The VR pilot project provides a sneak preview of planned structures and processes, increases planning accuracy in the early phases of a project and reduces planning time.

Employees are able to get a feel for their new workplace in a VR training space. VR goggles provide them with a glimpse of their new working environment and planned work processes. As a result, employees often come up with ideas for improvement that enable new operations to be optimised in advance and adapted for rollout.

From 28 August, systems will be refilled so production can resume after the break and, starting with the early shift on 7 September, vehicles can once again roll off the production lines at the main plant in Munich. Certain areas of the Munich plant, such as engine production, will continue to operate at full scale to secure supplies for the global production network.


The Latest News, Brought To You By
BMW Group Plant Munich gears up for fully-electric future
Modified on Wednesday 22nd July 2020
Find all articles related to:
BMW Group Plant Munich gears up for fully-electric future
TaaS Technology Magazine
Info
Uber, Mobilize, RATP And Blablacar Join Forces For Sustainable Mobility By Launching The “Mobilité360” Project
Construction Begins On First-of-its-kind Electric Vehicle Battery Technology Centre And Pilot Line
Ford Boosts Investment In Solid Power
AAM And REE Automotive To Jointly Develop New Electric Propulsion System
FEV Successful In Designing Low Emission, Efficient Hydrogen Internal Combustion Engine
EasyMile Raises €55 Million In Series B Round
Nikola And Total Transportation Services Inc. Sign LOI For 100 Nikola Trucks
Fisker Launches Resource For Environmental, Social, And Governance Policy, Practices And Reporting And
Nano One And Johnson Matthey Enter Into A Joint Development Agreement For Lithium-ion Battery Materials
Iteris Awarded $3.3 Million Contract By City Of Modesto For Smart Mobility Initiative
Former Google Head Of Energy Strategy Neha Palmer Joins TeraWatt Infrastructure
Dr. Matthias Jurytko Takes Over The Management Of The Fuel Cell Joint Venture Cellcentric
Pininfarina And MT Distribution Join Forces To Create A New Range Of Vehicles For Urban Electric Micro-mobility
Faction Raises $4.3M To Develop Light EV Driverless Fleets
SEAT Introduces Autonomous Mobile Robots In Its Barcelona Factory
Daimler Truck AG And Volvo Group Fully Committed To Hydrogen-based Fuel-cells – Launch Of New Joint Venture Cellcentric
Faraday Future Selects Velodyne As Exclusive Lidar Supplier For Flagship FF 91
PCB Depaneling: Laser Technology Improves Quality And Efficiency For Automotive Applications
Gilbarco Veeder-Root Expands E-mobility Platform With Launch Of EVerse
GHD Survey Reveals Half Of British Consumers Are Considering An Electric Vehicle In Next Five Years
Toshiba Expands Scope Of Its Solid-State LiDAR Solution To Address Transportation Infrastructure Monitoring
European Launch: NIO To Sell Smart Premium EVs In Norway
HELLA Brings Latest Passenger Car 77GHz Radar Technology Into Series Production
Renault Group And Plug Power Inc. Launch HYVIA
Info
Info
×
Search the news archive

To close this popup you can press escape or click the close icon.
Logo
×
Logo
×
Register - Step 1

You may choose to subscribe to the TaaS Magazine, the TaaS Newsletter, or both. You may also request additional information if required, before submitting your application.


Please subscribe me to:

 

You chose the industry type of "Other"

Please enter the industry that you work in:
Please enter the industry that you work in:
 
X
Info
X
Info
{taasPodcastNotification} Array
Live Event